For our latest update video we take a look at the work of our stonemasons and carpenters as they complete their work on the roof of the South Pavilion.
Work is progressing largely according to plan with just a couple of delays getting materials on site. During the month of May we should begin work on re-roofing the Pavilion, and when this work is completed, the scaffold can begin to be removed. One of the last jobs will be to replace the weathervane which was removed for restoration at the beginning of this project. We have another video planned which will cover the extensive work that was required to repair and restore this beautiful feature.